Pasa, Stein am Rhein

2020

Five new apartments were created in each of the two newly built apartment buildings in Stein am Rhein. Both houses consist of two full floors and a recessed attic floor.

Facts and images
Construction Data
Involved
The wooden structure is erected
The wooden structure is erected
Ceiling integrated steel joist
Ceiling integrated steel joist
CLT lift shaft
CLT lift shaft
View of the two houses
View of the two houses

The project
The upper floors are built entirely in wood. The exterior and interior walls consist of a timber frame construction, which transfers the loads from the floor slabs made of horizontal glulam. In the area of the balconies, slender steel columns were chosen for load transfer. The stairwell was made of encapsulated cross-laminated timber panels that meet the fire protection requirements for an emergency stairwell.

The construction
Precast concrete components were used only for the stair flights. The elevator shaft was also made of cross-laminated timber panels. This was initially erected in one piece over the entire height. The bracing was provided by the floor and wall slabs, which were formed with defined inner and outer walls. Underneath the two structures are the basement rooms and the underground garage.

The challenge
The exterior dimensions of the two multi-family buildings were adapted to the non-regular site layout. This results in irregular building footprints with sloping walls and recessed floors. The main challenge was the recessed attic floor, where the loads had to be transferred above the spacious living and dining area below. The loads could be transferred with the help of individual steel girders integrated in the floor slab.

Construction Data

- Glulam GL24 30 m3

- Glulam floor slabs 280 m3

- structural timber C24 55 m3

- Cross laminated timber panels 80 m3

- OSB boards 510 m2

- Gypsum fiberboards 2850 m2


Construction costs

- BKP 2: CHF 5'900'000.-

- BKP 214: CHF 950'000.-


Services of Timbatec

- SIA Phase 31 Preliminary design

- SIA Phase 32 Construction project

- SIA Phase 51 Implementation project

- SIA Phase 52 Execution

- Statics and construction

- Technical planning Building physics

- Fire protection Quality assurance QSS1

Client
GetSpace AG
8274 Tägerwilen


Architect
Klein und Müller Architekten AG
8280 Kreuzlingen


Timberconstruction engineer
Timbatec Holzbauingenieure (Schweiz) AG Bern
3012 Bern


Timberconstruction
Krattiger Holzbau & Planung GmbH
9517 Mettlen


Civil engineer
Ingenieurbüro Furrer & Partner AG
9500 Wil


Building physics
Timbatec Holzbauingenieure (Schweiz) AG Bern
3012 Bern


Datenschutzhinweis

Diese Webseite nutzt externe Komponenten welche dazu genutzt werden können, Daten über Ihr Verhalten zu sammeln.

Notwendige Cookies werden immer geladen